Analisis Gangguan Kelistrikan Pada Panel Kontrol Hoisting Crane Di Pabrik Kelapa Sawit Sei Daun PTPN 3, Hoisting Crane, Control Panel,Kontaktor...
Author: FAHRUL RAMADHAN
Date: 2024
Keywords: Hoisting Crane, Control Panel,Kontaktor
Type: Jurnal
Category: penelitian
The frequent issues encountered in the palm oil processing process at PTPN 3 Sei Daun primarily involve electrical disruptions in the hoisting crane control panel. These damages have adverse repercussions for the company, resulting in production halts. The objective of this research is to analyze the root cause of the issue and subsequently determine maintenance and efforts to anticipate these disruptions. One of the problems that often occurs is a damaged contactor, which results in it stopping the operation of the hoisting crane itsel. The expected outcome of this research is to minimize the occurring damage, optimize maintenance, and prevent breakdowns, allowing the company to optimize its palm oil processing.
Files:
Tidak ada data !
Collections:
Digital Library UNPAB